RAE Wastewater Treatment Plant

The project consisted of removing sewer lagoon cells and replacing them with a Sequential Batch Reactor (SBR) Treatment System.

This involved dismantling the lagoon cells, removing and disposing of sludge, and filling in existing lagoon cells. There was extensive dewatering of the site. Site excavation and grading was part of the SBR Building construction. A series of distribution piping was installed to enable the controlof flow of the effluent between concrete processing tanks. Mechanical and electrical components were installed that are involved.

Read Testimonial
  • Prime Contractor: DLM Contracting, Inc.
  • Year: 2003-2004
Location/Owner:
RAE Water and Sewer District
129 Percival Path
Bozeman, MT 59718
Engineer:
Allied Engineering Services
32 Discovery Lane
Bozeman, MT 59718
Contacts:
David King (RAE Manager)
Tel: 406-586-3930

Terry Threlkeld
Tel: 406-763-4185
  • Contract Estimate: $1,876,975.00
  • Final Contract Billed: $2,100,000.00